Monthly Initiative Update:
Summary of Achievements:
Milestones Reached:
Challenges/Blockers Faced:
TLDR: Most of our time was spent trying to set up the Safe stack locally in order to start developing the module.
Milestone Progress Snapshot [%]:
Provide a snapshot of progress for each milestone as of end of reporting period; August 30, 2024.
Targeted %* | Actual % | Comments | |
---|---|---|---|
Milestone I | 100% | 100% | |
Milestone II | 100% | 100% | |
Milestone III | 95-100% | 100% | |
Milestone IV | 0% |
*Targeted completion % is derived from the proposal timeline.
Month | Amount Due ($USD) | Executed |
---|---|---|
August | $8,000 USD | $0 |
CES Comment:
Safe Sign-Off:
Copying the demo here for visbility Pixel Android video.mp4
Approve - Lorny (OBRA DAO Commission) - Sept 12 2024