Monthly Initiative Update:
Summary of Achievements:
Milestones Reached:
Challenges/Blockers Faced:
Milestone Progress Snapshot [%]:
Provide a snapshot of progress for each milestone as of end of reporting period; September 30, 2024.
Targeted %* | Actual % | Comments | |
---|---|---|---|
Milestone I | 100% | 95% | Pending some feedback from SafeDAO reviewers. |
Milestone II | ~50% | 25% | Currently in the early stages of of report writing but progress is auditable. |
Milestone III | 0% | 15% | This milestone was originally blocked by Milestone II, however there has been internal discussion around parallelising efforts for both II and III to complete delivery of all milestones sooner. |
*Targeted completion % is derived from the proposal timeline
Month | Amount Due ($USD) | Executed |
---|---|---|
September | $10,000 USD | $10,000 |
On granting us view access to the milestone deliverable
CES Comment: