Monthly Initiative Update:

Milestone Progress Snapshot [%]:

Provide a snapshot of progress for each milestone as of end of reporting period; May 31, 2024.

Targeted %* Actual % Comments
Milestone I 100% 92 Actively exploring the potential of a larger scope of work to help bring SafeDAO fully onchain, as bringing the Guardian role onchain has brought up questions for the SafeDAO team regarding the ideal evolution of the overall SafeDAO structure
Milestone II 100% 35 See above
Milestone III 0% 0

*Targeted completion % is derived from the proposal timeline, understanding that some milestones may have been blocked from progression for valid reasons. These blockers are reflected in our reporting sheets.

Month Amount Due Executed
June $2,500 $2,500

CES Comment:

Safe Sign-Off:

Approved - Amy (OBRA DAO Commission) July 1, 2024

Approved - Lorny (OBRA DAO Commission) July 1, 2024