Milestone Progress Snapshot [%]:
Provide a snapshot of progress for each milestone as of end of reporting period; July 31, 2024.
Targeted %* | Actual % | Comments | |
---|---|---|---|
Milestone I | 100% | 100% | |
Milestone II | 100% | 95% | We identified new elements that needed to be developed, including updating our subgraphs to allow for pagination and fixing the issues needed to make our Sponsored Gas per Level feature work. |
Milestone III | 100% | 80% | Starting Partner Testing this week; after that, it should take ~2 weeks to be able to launch. |
Milestone IV | 100% | 50% | Collaborating with Optimism Unlimited (core Optimism team) to help amplify when we launch. |
*Targeted completion % is derived from the proposal timeline, and may not reflect any valid blockers. Understanding your message for an extension on deliverables here (as mentioned, no issue), please just note the rationale for each and expected new completion.
Month | Amount Due | Executed |
---|---|---|
July | $9,375 USD | $0 |
CES Comment:
Safe Sign-Off:
Approved - André (OBRA DAO Commission) August 8, 2024