Milestone Progress Snapshot [%]:

Provide a snapshot of progress for each milestone as of end of reporting period; June 30, 2024.

Targeted %* Actual % Comments
Milestone I 100% 100%
Milestone II 100% 90% All features are now working. Need to finalize adding the remaining badges and adding smaller elements like SEO and server optimizations.
Milestone III 100% 70% Need to complete UI testing and deploy to production at the account.superchain.eco domain.
Milestone IV 90-100% 40% We aim to have at least 1 paid partner for our initial launch trail. Superchain Raffle UI development has been completed; need to finalize SA integration to go live.

*Targeted completion % is derived from the proposal timeline, and may not reflect any valid blockers. These, if mentioned and approved, will be reflected on reporting tracking sheet.

Month Amount Due Executed
June $9,375 USD $9,375 USD

CES Comment:

Safe Sign-Off:

Approved - Amy (OBRA DAO Commission) July 1 2024

Approved - Andre (OBRA DAO Commission) July 3, 2024