Monthly Initiative Update:

Milestone Progress Snapshot [%]:

Provide a snapshot of progress for each milestone as of end of reporting period; 31, 2024.

Targeted %* Actual % Comments
Milestone I 100% 100%
Milestone II 100% 60% The Twitter spaces are scheduled for mid-August when partners return from Summer schedules.
Milestone III 100% 90% We’ve produced two more blogs this month. In August, we’ll produce a final blog and update the Start Kit with the three newly created blogs.
Milestone IV 100% 70% To complete this milestone, we’ll produce an updated starter kit in August and do another big push, which will likely result in at least three more Start Kit / Support requests.

*Targeted completion % is derived from the proposal timeline, and may not reflect any valid blockers. Understanding your message for an extension on deliverables here (as mentioned, no issue), please just note the rationale for each and expected new completion.

Month Amount Due Executed
July $6,250 USD $0

CES Comment:

Safe Sign-Off: