Monthly Initiative Update:

Milestone Progress Snapshot [%]:

Provide a snapshot of progress for each milestone as of end of reporting period; May 31, 2024.

Targeted %* Actual % Comments
Milestone I 100% 100% Completed all the items for module dev onboarding except 1 item which is pointed out in the proposed rescope.
Milestone II 100% ~60% Completed the development updates needed for the registry, updated docs, and demo - circulated to auditors.
Milestone III 80-90% ~ 30 % Deployed a few module Apps, targeted Base community, local DAO, and Builder TGs for adoption.
Milestone IV ~50% ~ 30 % Working with a few projects to understand the usecases and API requirements to integrate the modules

*Targeted completion % is derived from the proposal timeline, understanding that some milestones may have been blocked from progression for valid reasons. These blockers are reflected in our reporting sheets.

Month Amount Due Executed
June $15,000 $15,000

Follow-Up Details

On explaining the size of rescoping for Milestone 1 as it pertains to developer onboarding…

  1. The timeline to complete the initial onboarding to introduce devs to the onboarding docs while simultaneously upgrading the module standard was small.
  2. Introducing the Safe ecosystem documentation and new modular standards, along with the necessary infrastructure, took longer to collaborate with new developers than we initially anticipated. This was a key factor we underestimated when scoping the project at the beginning.
  3. We also focused on internal development of module and working with projects rather than independent devs to add quality output.
  4. We are currently targeting the communities through workshop which will add more exposure to module ecosystem rather than individual onboarding (Although we are yet to find out on the outcome quality)

We are happy to still update our goals of the m1 based on the outcome of these workshops in the coming weeks.


CES Comment: